In May 2009, students and staff began breaking ground to build a greenhouse for the science department. The greenhouse should be completed over the summer and be ready for students returning in the fall.
June 1, 2009 decomposed granite is added to the site
June 4, 2009 preparing the footings
June 5, 2009 - Framing begins
June 8, 2009 - Continued work on the metal frame